Wallboard started
So the wallboard guys have started and ... what a mess. I'll be staying home today to keep an eye on them. It's a bit strange to come home and find plaster foot steps all through the house and hand prints on the phone and refrigerator. So today I'll be working from home while they, hopefully, finish up.
Wednesday, August 15, 2007
Almost back together
Tuesday, August 14, 2007
Framers are back
The framing guys are back to fix up some things that the GC flagged and some things that the framing inspector flagged.
1) Box in second floor drain.
2) Install interior doors
3) Fill in gaps around doors and house.
4) Nail the double LVL beam from both sides (not just one)
5) Install fire blocking at the top of most first floor walls.
6) Install the new beam and double joists in kitchen ceiling.
7) Build a wall in attic space to install blue board on.
They arrived yesterday and started a bunch of these tasks and also napped next to the sandbox for a while. Later the kids had fun in the huge puddle in front of our house with the builders lunch trash.
We also found out that the cabinets would arrive the week of September 3rd. ARG!
1) Box in second floor drain.
2) Install interior doors
3) Fill in gaps around doors and house.
4) Nail the double LVL beam from both sides (not just one)
5) Install fire blocking at the top of most first floor walls.
6) Install the new beam and double joists in kitchen ceiling.
7) Build a wall in attic space to install blue board on.
They arrived yesterday and started a bunch of these tasks and also napped next to the sandbox for a while. Later the kids had fun in the huge puddle in front of our house with the builders lunch trash.
We also found out that the cabinets would arrive the week of September 3rd. ARG!
Thursday, August 09, 2007
Not much in a week.
The outside of the house if almost finished. We just need a garage door, but now we are moving on to interior work.
The framing inspection happened yesterday and the inspector didn't like how large of a span we had in the kitchen. So our contractor went back to the drawing board and came up with a plan that they will present to the inspector tomorrow. The plan is to add a beam that extends the wall between the kitchen and dining room all the way to the back of the house. This will split the joists in the kitchen from a 15ft. span to about 11ft and 4ft spans. Then they will double all the 11ft joists. One issue is that the electrical work has all been finished in this area so I hope they don't need to mess with it. Our contractor will be doing all of this with no extra cost to us since there was always a plan to add a beam in the kitchen anyway.
We also had a bit of a scare when the plumber told us that there was no mention of a heater in the mudroom. The contract clearly does not say that there is heat in the mudroom, but we discussed having heat in there with our contractor before we signed the contract. We found out today that they will be adding the heat in the mudroom with a change order. We are relieved because we were starting to feel like everything that we did was costing too much more money.
So, with all that there is not too much to show on the blog, but I thought I'd post some links to some of the appliances and accessories that we have chosen.
Refrigerator: Maytag or GE
Range: Maytag or GE
Microwave: Maytag or GE
Dishwasher: Bosch, Maytag or GE
Faucet:Price Pfister or Moen
The framing inspection happened yesterday and the inspector didn't like how large of a span we had in the kitchen. So our contractor went back to the drawing board and came up with a plan that they will present to the inspector tomorrow. The plan is to add a beam that extends the wall between the kitchen and dining room all the way to the back of the house. This will split the joists in the kitchen from a 15ft. span to about 11ft and 4ft spans. Then they will double all the 11ft joists. One issue is that the electrical work has all been finished in this area so I hope they don't need to mess with it. Our contractor will be doing all of this with no extra cost to us since there was always a plan to add a beam in the kitchen anyway.
We also had a bit of a scare when the plumber told us that there was no mention of a heater in the mudroom. The contract clearly does not say that there is heat in the mudroom, but we discussed having heat in there with our contractor before we signed the contract. We found out today that they will be adding the heat in the mudroom with a change order. We are relieved because we were starting to feel like everything that we did was costing too much more money.
So, with all that there is not too much to show on the blog, but I thought I'd post some links to some of the appliances and accessories that we have chosen.
Refrigerator: Maytag or GE
Range: Maytag or GE
Microwave: Maytag or GE
Dishwasher: Bosch, Maytag or GE
Faucet:Price Pfister or Moen
Monday, August 06, 2007
Plumbing and Framing
Tuesday, July 31, 2007
Siding Finished
Things have slowed down a bit this week. The exterior is almost finished as you can see. They have been doing some work on the second floor entry to the addition and lolly collumns in the basement. Other than that we hope that all the supplies are here to finish up all the little jobs they have to finish.

Friday, July 27, 2007
Second story connected.
Kitchen window installed
External view with all windows.
Thursday, July 26, 2007
No pictures today.
I left my camera at work today so I don't have any pictures for you, but nothing much happened that you can see anyway. They finished roofing most of the addition, finished siding the East wall of the addition (that's the gable end - the only one with all the windows in it), and the electrician came back to wire the addition. They should ahve the front window in tomorrow and the wiring finished...I hope. I don't think this old refrigerator can handle being shut off again.
Wednesday, July 25, 2007
Tuesday, July 24, 2007
Siding started.
Kitchen plans
Monday, July 23, 2007
Electricity Arrives
Kathleen and I had a busy morning - we met with the electrician at 7:30am to figure out where all the outlets, lights, and switches are going. Then we went over to Fitzgerald Tile in Woburn, MA and picked out three tile samples for the kitchen floor. The guys were busy today as well; The rear door in the kitchen looks like it is in and looks very good. The window frame looks better also. The shingles are going on the roof (in the back) and the mudroom is now all framed. Looks like rough framing is finished so it's time to cut another check to the G.C.



Saturday, July 21, 2007
Kitchen Window Frame
Friday, July 20, 2007
Cabinets have been Finalized.
The kitchen cabinets have been finalized and we have the plans. Kathleen came back form Maine with the kids yesterday for a couple days and last night we went up to check out the new space. It’s looking good, but a bit small – Oh Well. We have to figure where all the outlets and switches and that type of thing are going to go so the electrician can do that on MONDAY! Oh, ya, the roof is supposed to go on Monday also! They are cutting out the hole for the kitchen window right now. I’ll have pictures tonight when they are done.
Wednesday, July 18, 2007
New View
The Roof Takes Shape
Well with all the rain we were supposed to have today I think it lit a fire under Mike's butt. He got here this morning with one extra guy and they got right to work with the ridge of the roof so they could put up a tarp to cover everything in case it rained. I left for work feeling sure that they would leave early, but it turns out that they got a lot done. The ridge is up and they have framed and plywooded all the walls on the second story. Tomorrow we should see the dormer go in and the plywood go on the roof.